Contango to pour first gold from Alaska mine on July 8


In September 2020, Contango and Kinross formed the Peak Gold joint venture aimed at developing the namesake deposit (later renamed Manh Choh) located on top of a group of low hills in the northern part of the Tetlin lease.

The JV — led by Kinross as operator — subsequently completed the work leading to a feasibility study in 2022, followed by its successful permitting for the project and construction of the mine.

Mining operations commenced in August of 2023 and ore hauling started in November 2023, leading to a sizeable stockpile of ore at Kinross’ Fort Knox facilities ready to be processed through the mill.

As outlined on the JV’s website, the two small open pits comprising Manh Choh are estimated to be mined concurrently for about 4 to 5 years, producing about 225,000 ounces of gold a year.

Based on over 55,000 metres of drilling to date, the deposit currently has a defined resource of 9.2 million tonnes in the measured and indicated category averaging 4.1 g/t gold and 14 g/t silver, for 1.2 million oz. of contained gold and 4.2 million oz. contained silver.





Read More: Contango to pour first gold from Alaska mine on July 8

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Get more stuff like this
in your inbox

Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

Thank you for subscribing.

Something went wrong.